You are viewing the PKP Support Forum | PKP Home Wiki

Changing the period of time allowed for a review?

Are you responsible for making OJS work -- installing, upgrading, migrating or troubleshooting? Do you think you've found a bug? Post in this forum.

Moderators: jmacgreg, btbell, michael, bdgregg, barbarah, asmecher

Forum rules
The Public Knowledge Project Support Forum is moving to http://forum.pkp.sfu.ca

This forum will be maintained permanently as an archived historical resource, but all new questions should be added to the new forum. Questions will no longer be monitored on this old forum after March 30, 2015.

Changing the period of time allowed for a review?

Postby garde » Tue Jan 16, 2007 8:40 pm


In setup step 2, I made the following setting:

Review Time
The typical period of time allowed for reviews: 4 weeks
Note: Can be modified during the editorial process.

Although it says here that the typical period can be modified during the review process, I cannot find a way to do this - other than simply changing the date in the email to the reviewer, which causes the problem that the reply email from the reviewer will contain the original date again as well as the journal system still works with the original date throughout the whole editorial process.

Is there a better way to do this?

Kind regards
Posts: 17
Joined: Thu Mar 16, 2006 12:16 am

Postby asmecher » Wed Jan 17, 2007 11:16 am

Hi Sebastian,

You can click on the review's due date before the request email is sent to change the date that will appear in the email and be used for automated reminders.

Alec Smecher
Open Journal Systems Team
Don't miss the First International PKP Scholarly Publishing Conference
July 11 - 13, 2007, Vancouver, BC, Canada
Posts: 10015
Joined: Wed Aug 10, 2005 12:56 pm

Postby garde » Wed Jan 17, 2007 4:41 pm

Wow - that's great!